Miami-Dade County Public Schools
Procurement Management Services

Questions and Answers for bid: 085-FF04
(3)

Bid Number : 085-FF04  Opening Date : 10/31/2006
Bid Title : IT HARDWARE 
Buyer : L Leasburg-Kramer 
Subject : Response to Questions - Second List 
Question : See attached list 
Answer : See attached list 
Date Posted : 10/26/2006 7:25:07 PM 
Attachment : questions to responses 2.pdf

Bid Number : 085-FF04  Opening Date : 10/31/2006
Bid Title : IT Hardware 
Buyer : L Leasburg-Kramer 
Subject : Response to questions 
Question : 1) Due to the extension to the bid opening date - Will that impact the dates for the oral presentations? (originally specified in the RFP as 11/13 & 14) If so, what are the targeted dates & times? 2) Will an agenda with specific topics and/or timeframe assignments be sent in advance of the the oral presentations? If so, when?  
Answer : 1) The schedule has been altered due to the opening date extension. Committee will review RFP submissions 11/13 and 11/15. Presentations if requested will be 11/29 and 11/30. 2) The committee will advise those requested to present of the time allotment and topics to be addressed on Nov. 15th or 16th.  
Date Posted : 11/7/2006 2:46:29 PM 
Attachment :

Bid Number : 085-FF04  Opening Date : 10/31/2006
Bid Title : IT Hardware 
Buyer : L Leasburg-Kramer 
Subject : Response to question 
Question : Can you please provide me with the number of attendees who will be present at Orals?  
Answer : 15 
Date Posted : 11/28/2006 8:17:05 AM 
Attachment :

Back to Top