1. We only plan to bid on the Simplex equipment which is offered through this bid. On other equipment, we would not be able to offer competitive pricing. Is this acceptable?
2. We have noticed that some of the Simplex items requested on this bid are discontinued. Most of these items have direct replacements with newer technologies. What are the procedures for bidding these items as substitutions considering that the bid specifically says "No Substitute"?
3. Please verify that a Performance Security bond is not required for this bid. |